City of Johannesburg - Official website

   

QUICKHELP




City of Johannesburg

 NEWS

RELATED LINKS:

City Power to replace ageing network
CITY Power has launched Operation Vuselela, a project to upgrade Johannesburg's ageing electricity network.
Read more

Electricity distribution faces major shake-up
IT IS official. Eskom Distribution and municipal electricity distribution units are to be shut down to make way for new national government-owned distribution companies as part of a major restructuring drive.
Read more

Giving power to the people of the city
WITHIN the short space of its existence, City Power, the City-owned utility that distributes electricity to residential and corporate clients in Johannesburg, has managed to upgrade its infrastructure and improve street lighting and customer service.
Read more

Giving power to the city: the rise of MK
SOME 20 years ago, a young Mogwailane Kenneth Mohlala left his rural homestead on the outskirts of Steelpoort in Limpopo province for the beckoning lights of the City of Gold. Today Mohlala is acknowledged as the man who has made the city lights glow even brighter.
Read more

Initiatives in place
to cut power outages

CITY Power has drawn up comprehensive plans and financing allocations to refurbish and upgrade the city's ageing electricity infrastructure.

July 4, 2005

By Lucille Davie

CITY Power's switches are old enough to go to a museum - the originals were installed in 1937, which makes them grandfathers of 68.

However, this is to change over the next five years. City Power, the City's electricity provider, has come under intense pressure recently as the city has experienced a number of power outages over the past 18 months, resulting in businesses losing millions of rands.

The electricity utility, with a R675-million capital budget for 2005/06 (and a R3,6-billion operating budget), buys 85 percent of its electricity from Eskom and the balance from the Kelvin Power Station.

Silas Zimu, the head of operations at City Power, says 70 percent of outages are caused by the condition of the network, which is characterised by "aged, under-designed and technically obsolete infrastructure".

If the network were at an "acceptable level", outages would have been contained at around 8 percent.

Switches
Much of the network, he explains, dates back to 1937, with old-fashioned mechanical switches, inadequate monitoring and protection systems, plants that have exceeded their maximum life cycle, a lack of integration between systems, and SHER (safety, health and environmental risk) non-compliance.

In addition, different systems have been installed over the years. Up until recently some of those companies, like Siemens, were no longer represented in the country. Zimu says every company supplied its own unique design.

Outages, however, "will never go away", Zimu says, as there will always be unpredictable factors like fire or lightning.

City Power has undertaken a number of initiatives to reduce outages. It has developed a network master plan; undertaken Eskom pre-engineering studies; commissioned detailed audits from a number of manufacturers; and compiled an internal audit.

The master plan involves appointing:

  • PSW Consulting Engineers to assist in the preparation of short, medium and long-term transmission and distribution plans for the Midrand area;
  • NET Group Consulting Engineers to assist in the preparation of plans for the remainder of the metropolitan area, in particular loading and network problems in the Siemert Road, Randburg and Roodepoort areas; and
  • Eskom to do pre-engineering studies at Fordsburg, Prospect, Delta, Kelvin and Orlando substations.
Transformers
"There has not been much maintenance of transformers since 1936," says Zimu. Transformers usually have a 30-year life cycle, which means that those fitted in the 1930s should have been replaced in the 1960s.

Each year 10 transformers are being refurbished and 25 new transformers have been ordered. The city has a total of 250 transformers.

Another big problem is that the cable is aluminium, which is very attractive to metal thieves. Zimu says that recently five scrap dealers have been closed down, but have probably moved to Meyerton and re-opened their operations.

City Power spends millions on security at its plants.

Overriding all of this is a system in which Eskom supplies electricity to just under half of the city (Soweto and Alex and north as far as Diepsloot and Lanseria). City Power supplies the rest of the city, right down south to Ennerdale.

The system was run by seven electricity distributors until 2000, when City Power consolidated the disparate systems into one.

An audit of the substation transformers has identified 52 high-risk transformers. Their age indicates an "urgent need" for them either to be replaced or refurbished, a programme that is designed to eliminate the backlog by 2010 or sooner.

The refurbishment programme will drop the length of time the transformers are in service to acceptable levels.

Capital requirements
Capital requirements for the 2005 to 2010 period for the refurbishment and upgrading of high-voltage transformers stand at R1,1-billion, with a load growth of R381-million, giving a total of R1,5-billion.

Medium-voltage transformers require R532-million for refurbishment and upgrading, with an additional R70-million required for load growth, totalling R602-million.

The refurbishment and upgrading of low-voltage transformers should cost R100-million, with R32-million for load growth, totalling R132-million. The grand total required for the five-year period is about R2,245-billion.

Switchgear and protection schemes
A detailed audit of switchgear was undertaken by Rotek and Siemens. This revealed a "significant number" of high-risk switchboards, particularly oil-insulated units. A refurbishment and replacement programme was urgently needed, particularly for switches older than 25 years.

The ageing switchgear pose far more serious problems than the transformers. The back-up protection is out of specification in most cases; 70 percent of protection relays are older than 20 years, with no spares available; and, to cater for the complete set of protection requirements, the suite of electro-mechanical relays per line should be replaced with new electronic relays.

This has to be done because repairing and refurbishing electro-mechanical relays is not cost effective.

Furthermore, protection schemes and 40 percent of the over-current and earth fault relays had an error margin of about 60 percent.

Budget allocations
City Power has outlined a minimum budget required to clear backlogs in the next five years. The transformer allocation is R52-million for 2005/06, R25-million each for 2006/07 and 2007/08, and R22-million each for 2008/09 and 2009/10.

The allocation for switchgear is R45-million for each year until 2008; thereafter R30-million will be needed for 2008/09 and R12-million for 2009/10.

The allocation of protection equipment in 2005/06 stands at R19-million, with R15-million for 2006/07, R9-million for 2007/08, R7-million for 2008/09, and R2-million for 2009/10.

This produces a total cost for refurbishment and maintenance of R116-million for 2005/06, R85-million for 2006/07, R79-million for 2007/08, R59-million for 2008/09, and R36-million for 2009/10.

Besides plant and operating problems, some of the key challenges facing City Power are low payment levels, coupled with a poor billing system, illegal connections, meter tampering, theft and vandalism, and capital funding requirements.

Zimu says that the Soccer World Cup in 2010 is a risk if things are left as they are. This looks unlikely, however. Eskom is re-employing 30 000 former staff members to take old plants out of mothballing.

He says that City Power should be ready by 2007 with the refurbishment and replacement of plant.



Permission to use web site material
Publishers may use material from this site free of charge, as long as:
  • Credit is given to either the "City of Johannesburg website (www.joburg.org.za)" or to "Johannesburg News Agency (www.joburg.org.za)";
  • If the article is used online, a link is provided to the original article on this website;
  • The name of the article's author is acknowledged;
  • The webmaster is informed of how and where the material is used (fill in this brief online form).
Johannesburg News Agency is operated by BIG Media at 011-484-1400




  • Print this Page
  • Send an online postcard
  • E-mail this article to a friend
  • Help using Joburg.org.za
  • QUICK LINKS

    CONTACT US
    375-5555 for all your city queries
    375-5911 for emergencies
    E-mail the city
    HIGHLIGHTS
    Traffic reports
    Ridesmart, all about ride sharing. Click for more
    Arts Alive 2007
    BEE Database
    Suppliers Database
    Municipal bond
    Citichat
    2010 World Cup
    Urban Development Zone
    Student Council
    Volunteer
    Soweto
    Alex